The inauguration of the Rawalpindi Ring Road has been postponed for the ninth time, and this time no new date has been announced. The ceremony will now be held at 24 hours’ notice once work is complete, The Express Tribune reported on 14 November 2026.
Why the Rawalpindi Ring Road Is Delayed
- One interchange is not fully complete.
- Toll plazas and toll booths are unfinished.
- The computerised toll collection system and weigh stations are not ready.
According to the report, the Rawalpindi Ring Road Authority has told contractors to finish the last interchange and the full toll system, including booths, by the end of November. The road is expected to open to general traffic before the formal ceremony.
Cost and Background
| Item | Detail |
|---|---|
| Foundation stone | March 2022 |
| Inauguration delays | 9 times |
| Latest reported cost | Over Rs 52 billion (earlier Rs 51.32 billion) |
| New opening date | Not announced |
The project was first proposed about 24 years ago. Its cost has risen with each delay. The Tribune report did not quote a named official.
What It Means for Commuters
The Ring Road is meant to take heavy traffic away from GT Road and inner Rawalpindi. Until it opens, trucks and intercity traffic will keep using existing routes. Once it opens, it will be a tolled road, so drivers should expect to pay at the new plazas. We will update this page when an opening date is confirmed.